14 laporan ditemukan · 0 belum selesai
| NO | Tanggal / Petugas | Lokasi | Keterangan Aktivitas | Kondisi & Rekomendasi | Notifikasi | Dokumentasi | Status | Aksi |
|---|---|---|---|---|---|---|---|---|
| 1 |
02 Nov 2026
M. Zainudin
|
CCSU
CIGADING 1
|
9 pcs sovel lassan patah
|
RELEASE
REQUEST REPAIR
|
TIDAK | Completed |
||
| 2 |
02 Nov 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Sovel chain CC1 lasan patah 9pcs
|
RELEASE
REQUEST REPAIR
|
Medium 130000019387 |
Completed |
||
| 3 |
13 Jul 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Blade screw lepas 4 & banyak yang kendor
|
LAIK PAKAI
REQUEST FABRIKASI
|
- 130000018559 |
Completed |
||
| 4 |
13 Jul 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Cover shaft cc1 sebelah kanan terkikis mengakibatkan kan matrial bocor
|
LAIK PAKAI
REQUEST REPAIR
|
- 130000018547 |
Completed |
||
| 5 |
13 Jul 2026
M. Zainudin
|
CCSU
CIGADING 1
|
CCSU, braket cc1 retak sebelah kanan
|
LAIK PAKAI
REQUEST REPAIR
|
- 130000018474 |
Completed |
||
| 6 |
25 Jun 2026
Oka Aulia Yusuf
|
CCSU
CIGADING 1
|
Program preventif mekanik NDT chain CC2
-Di tambah sebelum nya jadi total NDT 124 titik (100℅) -Yang terindikasi lasan retak 50 titik (40.3℅) |
RELEASE
REQUEST GANTI
|
Medium | Completed |
||
| 7 |
05 Jun 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Penambahan NDT 33 titik dan indikasi krack bertambah 14 titik
Total untuk sementara dari 124 titik yang terNDT 88 titik dan terindikasi krack 32 titik |
RELEASE
REQUEST REPAIR
|
Medium 130000018269 |
Completed |
||
| 8 |
04 Jun 2026
Oka Aulia Yusuf
|
CCSU
CIGADING 1
|
Program NDT chain CC2
Dari total 124 titik chain, 55 titik di NDT terindikasi krack 18 titik. Request ganti |
RELEASE
REQUEST GANTI
|
Medium 130000018269 |
Completed |
||
| 9 |
23 May 2026
M. Zainudin
|
CCSU
CIGADING 1
|
"Hasil pengecekan preventif mekanik di area CC2 ditemukan 4 sovel patah, 3 sebelah kiri & 1 sebelah kanan. Request ganti"
|
RELEASE
REQUEST GANTI
|
Medium | Completed |
||
| 10 |
07 May 2026
Oka Aulia Yusuf
|
CCSU
CIGADING 1
|
Dudukan Rell Chain CC2 yang rusak di Crane CSU.
|
RELEASE
REQUEST REPAIR
|
Medium 130000018054 |
Completed |
||
| 11 |
07 May 2026
Oka Aulia Yusuf
|
CCSU
CIGADING 1
|
Team Preventive Supporting Mekanik Executor dengan melakukan pengecekan dan pembukaan cover nomor 2 dan nomor 3 untuk memastikan kondisi chain, rel, dan shovel di area CC2. Kerusakan yang ditemukan sudah langsung di eksekusi Eksekutor Mekanik
|
RELEASE
REQUEST REPAIR
|
TIDAK 130000018054 |
Completed |
||
| 12 |
05 May 2026
Ayu Andini
|
CCSU
CIGADING 1
|
Pengecekan Preventive dan Supporting Team Mekanik Executor di CC2 CSU
|
RELEASE
PREVENTIVE MAINTENANCE
|
TIDAK | Completed |
||
| 13 |
13 Mar 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Mengamankan patahan sovel CC2
CC2 sovel patah 1 pcs request ganti |
RELEASE
REQUEST GANTI
|
Medium | Completed |
||
| 14 |
13 Mar 2026
M. Zainudin
|
CCSU
CIGADING 1
|
Terdapat lubang pada dinding transfer material dari CC3 ke CC3 posisi di slip ring request perbaikan
|
RELEASE
REQUEST REPAIR
|
Medium | Completed |