| 1 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch closing
kondisi ok di GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 2 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch holding,
kondisi ok di GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 3 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch boom
kondisi ok di GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 4 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pengukuran suhu ruang panel elektrik GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 5 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll festune cabin operator GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 6 |
16 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pengencangan baud panel LSA CPA Gantry GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 7 |
16 Nov 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Cleaning dan lubrikasi roll pendulum medium voltage
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 8 |
16 Nov 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Cleaning dan lubrikasi zerospeed GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 9 |
12 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pengukuran suhu ruang panel elektrik GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 10 |
12 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch closing terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 11 |
12 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch holding terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 12 |
12 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch boom terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 13 |
12 Nov 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi motor gate Hooper GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 14 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch closing terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 15 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch holding terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 16 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch boom terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 17 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll festune cabin operator GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 18 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Kabel glend motor vibrating GSU 05 untuk saat ini masih terpantau amann
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 19 |
28 Oct 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll pendulum medium voltage GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 20 |
28 Oct 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Cleaning dan lubrikasi underspeed GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 21 |
28 Oct 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Pengencengan baut panel LSA CPA Gantry GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 22 |
22 Oct 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Melakukan inspeksi elektrik di area Dermaga 5, Pengecekan trafo, Panel power lampu penerangan, dan lampu penerangan. Kondisi lampu penerang D5 sudah OK (nyala) untuk semua tiang.
Tiang 1 dan 3 dari Anyer menggunakan fotocell (beda jalur dengan tiang lainnya).
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 23 |
22 Sep 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 2)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 24 |
22 Sep 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 1)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 25 |
22 Sep 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Pengukuran suhu ruang panel GSU-05 : 34.1°C
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 26 |
22 Sep 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pipa kabel lampu handrail hopper GSU-05 patah dan posisi ngegantung ke bawah (langsung action, pipa kabel sudah pada posisi sebelumnya)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
PANTAU |
|
Ready to Use |
|
| 27 |
22 Sep 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll festune cabin operator GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 28 |
17 Sep 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Hasil Megger Motor gantry GSU 05 no 01 sebelah laut , Oke
U1 - G : 550 Mohm
V1 - G : 550 Mohm
W1 - G : 550 Mohm
U2 - G : 550 Mohm
V2 - G : 550 Mohm
W2 - G : 550 Mohm
Antar Phase
U1 - U2 : 0 Mohm
U1 - V2 : 550 Mohm
U1 - W2 : 550 Mohm
V1 - V2 : 0 Mohm
V1 - U2 : 550 Mohm
V1 - W2 : 550 Mohm
W1 - W2 : 0 Mohm
W1 - U2 : 550 Mohm
W1 - V2 : 550 Mohm
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 29 |
17 Sep 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pengencangan baud panel LSA CPA Gantry GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 30 |
17 Sep 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Kabel glend motor vibrating GSU 05 luka/sobek , langsung action , sementara di rubber lalu di vinyl
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
PANTAU |
|
Ready to Use |
|
| 31 |
20 Aug 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 2)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 32 |
20 Aug 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 1)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 33 |
28 Jul 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 2)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 34 |
28 Jul 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 1)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 35 |
28 Jul 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Cleaning underspeed GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 36 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Kabel glend motor vibrating GSU 05 luka/sobek , langsung action , sementara di rubber lalu di vinyl
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 37 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Pengencangan baud panel LSA CPA Gantry GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 38 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll pendulum medium voltage GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 39 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Lubrikasi roll festune cabin operator GSU 05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 40 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch closing terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 41 |
28 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch holding terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 42 |
02 Jul 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Hasil Megger Motor Trolley GSU 05 :
U1 - G : 550 Mohm
V1 - G : 550 Mohm
W1 - G : 550 Mohm
U2 - G : 550 Mohm
V2 - G : 550 Mohm
W2 - G : 550 Mohm
Antar Phase
U1 - U2 : 0 Mohm
U1 - V2 : 550 Mohm
U1 - W2 : 550 Mohm
V1 - V2 : 0 Mohm
V1 - U2 : 550 Mohm
V1 - W2 : 550 Mohm
W1 - W2 : 0 Mohm
W1 - U2 : 550 Mohm
W1 - V2 : 550 Mohm
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 43 |
02 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Hasil Megger Motor closing GSU 05 :
U1 - G : 550 Mohm
V1 - G : 550 Mohm
W1 - G : 550 Mohm
U2 - G : 550 Mohm
V2 - G : 550 Mohm
W2 - G : 550 Mohm
Antar Phase
U1 - U2 : 0 Mohm
U1 - V2 : 550 Mohm
U1 - W2 : 550 Mohm
V1 - V2 : 0 Mohm
V1 - U2 : 550 Mohm
V1 - W2 : 550 Mohm
W1 - W2 : 0 Mohm
W1 - U2 : 550 Mohm
W1 - V2 : 550 Mohm
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 44 |
02 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Hasil Megger Motor holding GSU 05 :
U1 - G : 550 Mohm
V1 - G : 550 Mohm
W1 - G : 550 Mohm
U2 - G : 550 Mohm
V2 - G : 550 Mohm
W2 - G : 550 Mohm
Antar Phase
U1 - U2 : 0 Mohm
U1 - V2 : 550 Mohm
U1 - W2 : 550 Mohm
V1 - V2 : 0 Mohm
V1 - U2 : 550 Mohm
V1 - W2 : 550 Mohm
W1 - W2 : 0 Mohm
W1 - U2 : 550 Mohm
W1 - V2 : 550 Mohm
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 45 |
02 Jul 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Hasil Megger Motor Boom GSU 05 :
U1 - G : 180 Mohm
V1 - G : 174 Mohm
W1 - G : 140 Mohm
U2 - G : 150 Mohm
V2 - G : 160 Mohm
W2 - G : 170 Mohm
Antar Phase
U1 - U2 : 0 Mohm
U1 - V2 : 242 Mohm
U1 - W2 : 240 Mohm
V1 - V2 : 0 Mohm
V1 - U2 : 230 Mohm
V1 - W2 : 244 Mohm
W1 - W2 : 0 Mohm
W1 - U2 : 236 Mohm
W1 - V2 : 245 Mohm
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 46 |
02 Jun 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 2)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 47 |
02 Jun 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 1)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 48 |
21 May 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 2)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 49 |
21 May 2026
Hasyim Alhabsyi
|
GSU-05
CIGADING 2
|
Inspeksi dan Pengukuran suhu Vibrating (Motor 1)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|
| 50 |
21 May 2026
Anton Diki W
|
GSU-05
CIGADING 2
|
Chamswitch holding dan closing terpantau OK GSU-05
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK |
|
Ready to Use |
|