7 laporan ditemukan · 0 belum selesai
| NO | Tanggal / Petugas | Lokasi | Keterangan Aktivitas | Kondisi & Rekomendasi | Notifikasi | Dokumentasi | Status | Aksi |
|---|---|---|---|---|---|---|---|---|
| 1 |
14 Nov 2026
Anton Diki W
|
Conveyor PBCN 2
CIGADING 1
|
Dudukan sling pullcord di conveyor PBCN 02 tidak terpasang di conveyor nomor 80 , rekues pasang
|
RELEASE
BY EXECUTOR
|
Medium 130000019553 |
Completed |
||
| 2 |
14 Nov 2026
Hasyim Alhabsyi
|
Conveyor PBCN 2
CIGADING 1
|
Cleaning motor drive
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK | Ready to Use |
||
| 3 |
14 Aug 2026
Anton Diki W
|
Conveyor PBCN 2
CIGADING 1
|
Belt rip PBCN-02 perlu identifikasi lanjutan pengecekan jalur kabel/inputan dari relay ke PLC di panel tower 11.
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
PANTAU | Ready to Use |
||
| 4 |
14 Aug 2026
Hasyim Alhabsyi
|
Conveyor PBCN 2
CIGADING 1
|
Zerospeed GSU-01 kemasukan semut, langsung di cleaning
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK | Ready to Use |
||
| 5 |
17 Jul 2026
Hasyim Alhabsyi
|
Conveyor PBCN 2
CIGADING 1
|
Cleaning motor drive PBCN-02
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK | Ready to Use |
||
| 6 |
29 May 2026
Hasyim Alhabsyi
|
Conveyor PBCN 2
CIGADING 1
|
Program pengujian tahanan isolasi (megger test) motor drive PBCN2, motor brake, dan motor fan. Hasil pengujian nilainya masih OK (550 MOhm)
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK | Ready to Use |
||
| 7 |
28 Apr 2026
Hasyim Alhabsyi
|
Conveyor PBCN 2
CIGADING 1
|
Lubrikasi zero speed GSU-01 dan GSU-04 sisi laut dan sisi darat conveyor PBCN-02
|
LAIK PAKAI
PREVENTIVE MAINTENANCE
|
TIDAK | Ready to Use |