Rekap Semua Kondisi

306 laporan ditemukan · 126 belum selesai

Reset
Mekanik 306 126 belum selesai · 180 lainnya

Mekanik

306 laporan · 126 belum selesai
NO Tanggal / Petugas Lokasi Keterangan Aktivitas Kondisi & Rekomendasi Notifikasi Dokumentasi Status Aksi
1
21 Nov 2026
M. Zainudin
GSU-04
CIGADING 1
Program running inspection GSU 4
- gantry unit
- discharging unit
- Trolley unit
- holding closing unit
Hasil inspection kondisi alat layak pakai
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
2
21 Nov 2026
M. Zainudin
GSU-01
CIGADING 1
Program running inspection GSU 1 & 4
- gantry unit
- discharging unit
- Trolley unit
- holding closing unit
Hasil inspection kondisi alat layak pakai
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
3
20 Nov 2026
M. Zainudin
Feeding SGT
CIGADING 1
Preventif program shutdown inspection area bungker feeding SGT
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
4
19 Nov 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Preventif mekanik Program inspection A102, kondisi masih aman
- konstruksi
- belt conveyor
- roll top, roll return
- fram roll
- drum pulley
- brake sistem
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi Dokumentasi
Ready to Use
5
18 Nov 2026
M. Zainudin
DLLC-03
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 4:
- Gantry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
6
18 Nov 2026
M. Zainudin
DLLC-04
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 4:
- Gantry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
7
18 Nov 2026
Oka Aulia Yusuf
DLLC-04
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 4:
- Gantry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi Dokumentasi
Ready to Use
8
17 Nov 2026
M. Zainudin
Grabe Cigading 2
CIGADING 2
Program running inspection Grabe cigading 2
kondisi masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
9
16 Nov 2026
M. Zainudin
GSU-05
CIGADING 2
Pulley holding bagian anyer retak di Auxtrolley unit di gsu 05
RUSAK BERAT
REQUEST REPAIR
Emergency
130000019532
Dokumentasi
In Process
10
16 Nov 2026
M. Zainudin
GSU-06
CIGADING 2
Wire rope closing gsu 6 rantas 2kwt/strnd-6d/12kwt (jarak +-20 meter dari mangkok, sisa di drum masih banyak
RUSAK BERAT
REQUEST GANTI
Emergency
130000019592
Dokumentasi
In Process
11
16 Nov 2026
M. Zainudin
GSU-06
CIGADING 2
Pulley holding bagian anyer retak di Auxtrolley unit di gsu 6
RUSAK RINGAN
REQUEST REPAIR
Emergency
130000019591
Dokumentasi
In Process
12
16 Nov 2026
M. Zainudin
GSU-06
CIGADING 2
Rail trolley bagian anyer retak di gsu 6. Req repair
RUSAK RINGAN
REQUEST REPAIR
Emergency
130000019590
Dokumentasi
In Process
13
16 Nov 2026
M. Zainudin
CCSU
CIGADING 1
Running inspection csu, kondisi masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
14
12 Nov 2026
M. Zainudin
GSU-06
CIGADING 2
Program shutdown inspection GSU 6
- gantry unit
- discharging sistem
- trolley unit
- holding closing
- motor room area
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
15
12 Nov 2026
M. Zainudin
GSU-05
CIGADING 2
Program shutdown inspection GSU 5
- gantry unit
- discharging sistem
- trolley unit
- holding closing
- motor room area
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
16
11 Nov 2026
M. Zainudin
GSU-01
CIGADING 1
GSU 1 plat Hopper bagian darat rusak request perbaikan
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
17
11 Nov 2026
M. Zainudin
GSU-01
CIGADING 1
Roll prepenting rusak bagian merak di maintrolley unit gsu 1. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
Dokumentasi
Outstanding
18
10 Nov 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Dinding bucket grab P5 bagian darat ada yg tipis & bolong di cigading 2. Request repair
RUSAK RINGAN
REQUEST REPAIR
Low
Dokumentasi
Outstanding
19
09 Nov 2026
M. Zainudin
DLLC-02
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 02
- Gabtry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
20
09 Nov 2026
M. Zainudin
DLLC-01
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 01
- Gabtry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
21
07 Nov 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
PHC 2 wire rope holding rantas 1kwt/strnd - 6kwt/6d ( pantau)
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
22
07 Nov 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
PHC 2 kampas brake holding tipis sebelah (pantau)
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
23
07 Nov 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
PHC 2 wire rope counter weight rantas 2kwt/strnd - 5kwt/6d (pantau)
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
24
07 Nov 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
PHC 2 gearbox gantry butuh tambah grease
LAIK PAKAI
REQUEST PENAMBAHAN
Low
130000019487
Dokumentasi
Completed
25
07 Nov 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Stopbar track gear boom bagian kanan & kiri pecah di phc 1. Req ganti
RUSAK RINGAN
REQUEST GANTI
Low
130000019483
Dokumentasi
In Process
26
07 Nov 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
PHC 1 gearbox gantry kering request penambahan pelumas
RELEASE
BY EXECUTOR
Low
130000019484
Dokumentasi
Completed
27
05 Nov 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventif mekanik program inspection mekanikal sistem di conveyor 102
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
28
05 Nov 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll pembalik no 588 bagian anyer tabungnya patah di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Low
130000019376
Dokumentasi
In Process
29
05 Nov 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll pembalik no 641 bagian anyer macet di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Low
130000019376
Dokumentasi
In Process
30
04 Nov 2026
M. Zainudin
DLLC-03
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 3 & 4 :
- Gabtry unit
- Discharging sistem
- Wire rope holding, closing
- Brake sistem holding, closing, luffing, slewing
- Gear slewing, luffing
- Autolube
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
31
04 Nov 2026
M. Zainudin
DLLC-04
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 4
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
32
04 Nov 2026
M. Zainudin
DLLC-03
CIGADING 1
Preventif mekanik program inspection mekanikal sistem DLLC 3
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
33
03 Nov 2026
M. Zainudin
Conveyor A103
CIGADING 2
Preventif mekanik running inspection A103 & TFH
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
34
03 Nov 2026
M. Zainudin
Conveyor A103
CIGADING 2
Preventif mekanik running inspection A103 & TFH
Kondisi Alat sementara Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
35
02 Nov 2026
M. Zainudin
CCSU
CIGADING 1
9 pcs sovel lassan patah
RELEASE
REQUEST REPAIR
TIDAK
Dokumentasi Dokumentasi
Completed
36
02 Nov 2026
M. Zainudin
CCSU
CIGADING 1
Sovel chain CC1 lasan patah 9pcs
RELEASE
REQUEST REPAIR
Medium
130000019387
Dokumentasi Dokumentasi
Completed
37
02 Nov 2026
M. Zainudin
CCSU
CIGADING 1
NDT chain CCSU di area CC1 ( 42 ocs NDT ok )
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
38
29 Oct 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll pembalik no 512 bagian merak tabungnya bolong di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Low
130000019140
Dokumentasi
In Process
39
28 Oct 2026
M. Zainudin
GSU-06
CIGADING 2
Grabe P5 rantas 2kwt/strnd-6d/13kwt posisi grabe di gsu 06
RUSAK BERAT
REQUEST GANTI
No Priority
130000019318
Dokumentasi Dokumentasi
In Process
40
28 Oct 2026
M. Zainudin
GSU-06
CIGADING 2
Kontruksi area leadsead lasnya retak
RUSAK RINGAN
REQUEST REPAIR
No Priority
130000019319
Dokumentasi
In Process
41
28 Oct 2026
M. Zainudin
GSU-06
CIGADING 2
GSU 6 shaft pulley auxtrolley unit sebelah merak bosing lepas
RUSAK BERAT
REQUEST REPAIR
Emergency
130000019316
Dokumentasi Dokumentasi
In Process
42
28 Oct 2026
Oka Aulia Yusuf
GSU-06
CIGADING 2
Pulley holding bagian anyer retak di pivot unit gsu 6. Req repair
RUSAK RINGAN
REQUEST REPAIR
Low
130000019249
Dokumentasi
In Process
43
28 Oct 2026
Oka Aulia Yusuf
GSU-06
CIGADING 2
Rail trolley bagian anyer retak di gsu 6. Req repair
RUSAK RINGAN
REQUEST REPAIR
Low
130000019250
Dokumentasi
In Process
44
28 Oct 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope auxtrolley alur kiri rantas 3kwt/st130000019317r 6d=12kwt di gsu 5. Req ganti
RUSAK RINGAN
REQUEST GANTI
Low
130000019317
Dokumentasi
In Process
45
28 Oct 2026
M. Zainudin
GSU-04
CIGADING 1
Program preventif mekansiytem di Gsu
Kondisi Alat sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
46
27 Oct 2026
Oka Aulia Yusuf
GSU-06
CIGADING 2
GSU 6 dudukan rubber suspension sebelah laut-merak las2an retak (request repair)
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019306
Dokumentasi
In Process
47
27 Oct 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Dinding bucket grab C2 ada yg bolong di cigading 2. Request repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019305
Dokumentasi
In Process
48
26 Oct 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Baut running wheel counter weight bagian atas darat patah 2 pcs di phc 1. Req ganti
RELEASE
REQUEST REPAIR
Medium
130000019290
Dokumentasi
Completed
49
26 Oct 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Baut running wheel counter weight bagian bawah darat patah 2 pcs di phc 1. Req ganti
RELEASE
REQUEST REPAIR
Medium
130000019290
Dokumentasi
Completed
50
24 Oct 2026
M. Zainudin
DLLC-04
CIGADING 1
DLLC 4 wire rope holding rantas 1kwt/strnd-3kwt/6d
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
51
24 Oct 2026
M. Zainudin
DLLC-04
CIGADING 1
Preventive mekanisytem di DLLC untuk mekanisytem seperti gearslwing, gentry,grase, dan brake sistem sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
52
24 Oct 2026
M. Zainudin
DLLC-04
CIGADING 1
DLLC 4 wire rope closing rantas 3kwt/strnd-10kwt/6d
RUSAK BERAT
REQUEST GANTI
Emergency
130000019271
Dokumentasi Dokumentasi
In Process
53
24 Oct 2026
Oka Aulia Yusuf
DLLC-03
CIGADING 1
Open gear gantry kering di DLLC 3. Request lubrikasi
LAIK PAKAI
REQUEST PENAMBAHAN
Medium
130000019282
Dokumentasi
Completed
54
24 Oct 2026
Oka Aulia Yusuf
DLLC-03
CIGADING 1
Stopbar gantry bagian laut/anyer pecah di dllc 3. request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018696
Dokumentasi
In Process
55
24 Oct 2026
Oka Aulia Yusuf
DLLC-03
CIGADING 1
Stopbar gantry bagian darat/anyer pecah di dllc 3. request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018697
Dokumentasi
In Process
56
23 Oct 2026
M. Zainudin
Feeding SGT
CIGADING 1
Sporting Tim vulkanisir pergantian buckeat fieding SGT
RUSAK BERAT
REQUEST GANTI
No Priority
130000019240
Dokumentasi Dokumentasi
In Process
57
23 Oct 2026
Oka Aulia Yusuf
Feeding SGT
CIGADING 1
Dinding bucket elevator bagian atas ada yg bolong di fiding sgt. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019355
Dokumentasi
In Process
58
22 Oct 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Karet legging drum snub head pulley terkelupas di A102. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019356
Dokumentasi
In Process
59
21 Oct 2026
M. Zainudin
CCSU
CIGADING 1
Preventif mekanisytem di CCSU
Kondisi Sementara alat masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
60
20 Oct 2026
M. Zainudin
Conveyor A103
CIGADING 2
Program preventif mekanisytem di 103
Kondisi Alat mekanisytem sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
61
19 Oct 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Wire rope counterweight rantas 3kwt/str 6d=6kwt di phc 2. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
62
19 Oct 2026
M. Zainudin
PHC-01
CIGADING 1
Anak tangga grabe di PHC 01 Indikasi anak tangga patak
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019357
Dokumentasi
In Process
63
17 Oct 2026
M. Zainudin
DLLC-01
CIGADING 1
Wire rope holding rantas 3kwt/str 6d=6kwt di dllc 1
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
64
17 Oct 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Anak tangga grab G4 lepas 2 pcs & lasing nya putus posisi grab di dllc 1. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018350
Dokumentasi
In Process
65
16 Oct 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Potong wire rope closing GSU05 yang rantas +/- 30 meter
RUSAK BERAT
REQUEST GANTI
High
130000019235
Dokumentasi
In Process
66
15 Oct 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wheel brake gantry GSU 05 LS indikasi tidak ada pressure, isi oli OK. Request service dan ganti selang dan pompa
RUSAK RINGAN
REQUEST GANTI
Medium
130000019228
Dokumentasi
In Process
67
15 Oct 2026
Oka Aulia Yusuf
GSU-06
CIGADING 2
Pressure gauge powerpack wheel brake gantry rusak bagian darat & laut di gsu 6. request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000019229
Dokumentasi
In Process
68
15 Oct 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Pressure gauge powerpack wheel brake gantry rusak bagian darat & laut di gsu 5 . request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000019230
Dokumentasi
In Process
69
14 Oct 2026
M. Zainudin
DLLC-04
CIGADING 1
Program preventif mekanisytem di dllc
Kondisi sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
70
08 Oct 2026
M. Zainudin
Conveyor A101
CIGADING 2
Preventif mekanisytem di area Grabe dan conveyor 101 kondisi sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
71
08 Oct 2026
M. Zainudin
GSU-06
CIGADING 2
Wire rope holding rantas 3 kwt/str 6d=12kwt spare di drum masih ada di gsu 6.
RUSAK BERAT
REQUEST GANTI
Medium
130000019181
Dokumentasi
In Process
72
08 Oct 2026
M. Zainudin
GSU-05
CIGADING 2
Wire rope maintrolley alur kanan sebelah anyer rantas 3kwt/str 6d=10kwt di gsu 5
RUSAK BERAT
REQUEST GANTI
Medium
130000019180
Dokumentasi
In Process
73
07 Oct 2026
M. Zainudin
DLLC-03
CIGADING 1
Karet stokbard Dllc 03 indikasi pecah kiri-kanan arah anyer
RUSAK BERAT
REQUEST GANTI
Medium
130000018696
Dokumentasi Dokumentasi
In Process
74
07 Oct 2026
M. Zainudin
DLLC-03
CIGADING 1
Handrail di samping cabin operator indikasi Lepas lasanya di DLLC-03
RELEASE
REQUEST REPAIR
Medium
130000019174
Dokumentasi Dokumentasi
Completed
75
05 Oct 2026
M. Zainudin
CCSU
CIGADING 1
Preventif mekanik sistem di Ccsu kondisi sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
76
03 Oct 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Track gear boom di PHC 1 kering. Request lubrikasi
LAIK PAKAI
REQUEST PENAMBAHAN
Medium
130000019358
Dokumentasi
Completed
77
03 Oct 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Oli power pack closing PHC 2 perlu penambahan
LAIK PAKAI
REQUEST PENAMBAHAN
Medium
130000019154
Dokumentasi
Completed
78
29 Sep 2026
Oka Aulia Yusuf
Conveyor A101
CIGADING 2
Karet legging drum bend head pulley tipis di A101. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019111
Dokumentasi
In Process
79
28 Sep 2026
M. Zainudin
CCSU
CIGADING 1
Preventif mekanik sistem di Ccsu Sementara kondisi masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
80
26 Sep 2026
M. Zainudin
DLLC-04
CIGADING 1
Wire rope closing rantas 3kwt/str 6d=6kwt di dllc 4
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
81
26 Sep 2026
M. Zainudin
DLLC-03
CIGADING 1
Oli gate hopper DLLC 3 sebelah darat oli berkurang perlu penambahan
LAIK PAKAI
REQUEST PENAMBAHAN
Medium
130000019094
Dokumentasi
Completed
82
26 Sep 2026
M. Zainudin
DLLC-03
CIGADING 1
Program inspeksi mekanikal sistem DLLC 3 & 4
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
83
24 Sep 2026
M. Zainudin
Conveyor A102
CIGADING 2
Pintu ruang panel P1B bolong, indikasi terdapat rembesan dari tumpahan air dari bagian bawah karena kanopi pintu sudah korosi dan bolong. Req. Repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019252
Dokumentasi Dokumentasi
In Process
84
24 Sep 2026
Oka Aulia Yusuf
Conveyor A103
CIGADING 2
Roll pembalik no 74 bagian merak tabungnya patah di A103. Request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018859
Dokumentasi
In Process
85
23 Sep 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Wire rope counterweight rantas 3kwt/str 6d=6kwt di phc 2. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
86
23 Sep 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Wire rope counterweight rantas 2kwt/str 6d=6kwt di phc 1. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
87
22 Sep 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventif mekanik sistem di Area 102
Untuk mekanik sistem roll, belt dan dram kondisi masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
88
19 Sep 2026
M. Zainudin
GSU-04
CIGADING 1
Belt feeder di gsu 04 indikasi terkelupas pinggirannya
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019017
Dokumentasi
In Process
89
19 Sep 2026
M. Zainudin
GSU-04
CIGADING 1
Preventif mekanik sistem di Gsu 04
Untuk wire rope, pulley dan brake sytem
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
90
17 Sep 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope maintrolley alur kanan rantas 3 kwt/str 6d=8kwt di gsu 5. Pantau
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
91
17 Sep 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope closing rantas 3kwt/str kondisi dekat dengan mangkok/socket di GSU 5. Pantau
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
92
17 Sep 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Kondisi gearbox holding ad yg gompal di gsu 5. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
93
17 Sep 2026
Oka Aulia Yusuf
Conveyor A101
CIGADING 2
Karet legging drum tail pulley bagian pinggir darat ad yg terkelupas di A101. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018999
Dokumentasi
In Process
94
17 Sep 2026
M. Zainudin
Conveyor A101
CIGADING 2
Preventif mekanik sistem Grabe dan Conveyor 101
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
95
17 Sep 2026
M. Zainudin
GSU-05
CIGADING 2
Kondisi gearbox Closing GSU 05
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
96
17 Sep 2026
M. Zainudin
GSU-06
CIGADING 2
Kondisi gearbox Closing GSU 6.
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
97
17 Sep 2026
M. Zainudin
GSU-05
CIGADING 2
Kondisi gearbox holding ad yg gompal di gsu 5
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
98
16 Sep 2026
M. Zainudin
DLLC-02
CIGADING 1
Karat stokbar gentrie dllc 02 indikasi pecah
RUSAK RINGAN
REQUEST GANTI
Medium
Dokumentasi
Outstanding
99
16 Sep 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Fiber pengarah wire rope closing ad yg pecah 1 pcs & yg macet 6 pcs di dllc 1. Req ganti
LAIK PAKAI
REQUEST GANTI
Medium
130000018982
Dokumentasi
Completed
100
14 Sep 2026
Oka Aulia Yusuf
DLLC-04
CIGADING 1
Handrail hopper bagian laut rusak di dllc 4. Req repair
RELEASE
REQUEST REPAIR
Medium
130000018983
Dokumentasi
Completed
101
14 Sep 2026
M. Zainudin
DLLC-03
CIGADING 1
Kondisi mekanik sistem seperti wire rope, bearing dan pulley
Sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
102
14 Sep 2026
M. Zainudin
DLLC-03
CIGADING 1
Gear Slweing kering. Request lubrikasi di dllc 03
RELEASE
REQUEST SERVICE
Medium
Dokumentasi
Completed
103
08 Sep 2026
M. Zainudin
Grabe Cigading 2
CIGADING 2
Pengecekan wire rope grab all cigading 2 kondisi masih aman
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
104
08 Sep 2026
M. Zainudin
GSU-05
CIGADING 2
A101 roll pembalik no187 bagian darat patah
RUSAK BERAT
REQUEST GANTI
Medium
130000018863
Dokumentasi
In Process
105
08 Sep 2026
M. Zainudin
GSU-05
CIGADING 2
Wire rope auxtrolley rantas yg alur kiri sebelah anyer 2kwt/str 6d=2kwt di GSU 5
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
106
08 Sep 2026
M. Zainudin
GSU-05
CIGADING 2
Wire rope maintrolley alur kanan rantas 3kwt/str 6d=4kwt di gsu 5
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
107
08 Sep 2026
M. Zainudin
GSU-06
CIGADING 2
GSU 6 Pulley holding area pivot sebelah anyer lasan retak
RUSAK RINGAN
REQUEST REPAIR
Medium
130000019249
Dokumentasi
In Process
108
07 Sep 2026
M. Zainudin
GSU-01
CIGADING 1
GSU 4 wire rope auxtrolley rantas 5kwt/strnd-20kwt/6d
RELEASE
BY EXECUTOR
Medium
130000018966
Dokumentasi
Completed
109
05 Sep 2026
M. Zainudin
PHC-02
CIGADING 1
Wire rope counterweight rantas 4 kwt/str 6d=4kwt di phc 2. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
110
04 Sep 2026
M. Zainudin
Conveyor BCNO
CIGADING 1
Baud brake tromol indikasi patah dan rusak
RELEASE
REQUEST GANTI
Medium
130000018967
Dokumentasi
Completed
111
03 Sep 2026
M. Zainudin
DLLC-01
CIGADING 1
Gear slewing DLLC 1 kering request lubrikasi
LAIK PAKAI
REQUEST PENAMBAHAN
-
130000018774
Dokumentasi
Completed
112
01 Sep 2026
M. Zainudin
DLLC-04
CIGADING 1
Wire rope closing rantas tiga kawat/strand total 5kawat 6D Pantau
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
113
01 Sep 2026
M. Zainudin
DLLC-04
CIGADING 1
Pengecekan grabe dllc 04 kondisi sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
114
31 Aug 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Pinlok O-ring indikasi patah di gsu 04 request repair
RELEASE
REQUEST REPAIR
Medium
130000018851
Dokumentasi
Completed
115
31 Aug 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Conection closing aus bag anyer request ganti di gsu 04
RELEASE
REQUEST GANTI
Medium
130000018850
Dokumentasi
Completed
116
31 Aug 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
GSU 4 wire rope maintrolley alur kanan sebelah merak rantas 3kwt/strnd-12kwt/6d (ganti)
RELEASE
REQUEST GANTI
Medium
130000018849
Dokumentasi
Completed
117
31 Aug 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
GSU 4 wire rope spring rantas 4kwt/strnd-20kwt/6d ( ganti)
RELEASE
REQUEST GANTI
Medium
130000018848
Dokumentasi
Completed
118
31 Aug 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
Stop bar maintrolley bagian waterside(ws) anyer pecah/rusak di gsu 1. Req ganti
RELEASE
REQUEST GANTI
Medium
130000018846
Dokumentasi
Completed
119
31 Aug 2026
Oka Aulia Yusuf
Grabe Cigading 1
CIGADING 1
Wire rope grab C3 rantas 8kwt/str 6d=25kwt posisi grab di gsu 1. Req ganti
RELEASE
REQUEST GANTI
Medium
130000018847
Dokumentasi
Completed
120
31 Aug 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
Ruang panel room elektrik atapnya jebol (ditakutkan kemasukan tikus/air), rekues repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017157
Dokumentasi Dokumentasi
In Process
121
31 Aug 2026
M. Zainudin
Conveyor A103
CIGADING 2
Dram Bend head 2 leginganya terkelupas di conveyor A103
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018854
Dokumentasi
In Process
122
31 Aug 2026
M. Zainudin
Dermaga 6
CIGADING 2
Cover bandul countriwek 103 indikasi korosi
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018853
Dokumentasi
In Process
123
31 Aug 2026
M. Zainudin
Dermaga 6
CIGADING 2
Baud dan Kontruksi 103 area countriwek indikasi korosi request repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018852
Dokumentasi
In Process
124
31 Aug 2026
M. Zainudin
Conveyor A103
CIGADING 2
Roll pembalik no 76 indikasi belah jadi 2 di area conveyor A103
RUSAK BERAT
REQUEST GANTI
Medium
130000018651
Dokumentasi
In Process
125
28 Aug 2026
M. Zainudin
GSU-05
CIGADING 2
Wire rope holding GSU 5 rantas 4kwt/strnd-12kwt/6d,
Jarak 5 meter dari grabe, masih ada sisa spare di drum request potong
RUSAK BERAT
REQUEST GANTI
Medium
130000018824
Dokumentasi
In Process
126
28 Aug 2026
M. Zainudin
GSU-05
CIGADING 2
Pulley closing di area pifot bagian Anyer retak di GSU 5
RUSAK BERAT
REQUEST REPAIR
Medium
130000018826
Dokumentasi
In Process
127
27 Aug 2026
M. Zainudin
Conveyor A102
CIGADING 2
A102 bresing no 657 sudah korosi
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018828
Dokumentasi
In Process
128
27 Aug 2026
M. Zainudin
Conveyor A102
CIGADING 2
A102 bresing no 726 bagian anyer retak patah
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018827
Dokumentasi
In Process
129
26 Aug 2026
M. Zainudin
Grabe Cigading 1
CIGADING 1
Wire rope grab G1 rantas 5kwt/str 6d=17kwt posisi grab di phc 1
RELEASE
REQUEST GANTI
Medium
130000018812
Dokumentasi
Completed
130
26 Aug 2026
M. Zainudin
PHC-02
CIGADING 1
Wire rope countrwik rantas 3kwt/str 6d=5kwt di phc 2
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
131
26 Aug 2026
M. Zainudin
PHC-02
CIGADING 1
Baud runningwheel counterweight patah 1pcs di PHC 2
RELEASE
REQUEST GANTI
Medium
130000018822
Dokumentasi
Completed
132
24 Aug 2026
M. Zainudin
PHC-01
CIGADING 1
Pintu motoroom indikasi rusak dan korosi
RELEASE
REQUEST REPAIR
Medium
Dokumentasi
Completed
133
24 Aug 2026
M. Zainudin
PHC-01
CIGADING 1
Baud runningwheel counterweight patah 1pcs di PHC 1
LAIK PAKAI
REQUEST GANTI
-
130000018822
Dokumentasi
Completed
134
20 Aug 2026
Oka Aulia Yusuf
TFH & Feeding
CIGADING 2
Roll top no 54 arah darat macet di TFH. Request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
Dokumentasi
Outstanding
135
15 Aug 2026
M. Zainudin
GSU-06
CIGADING 2
GSU 6 Maintrolley rantas 1kwt/strnd - 2kwt/6D
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
136
15 Aug 2026
M. Zainudin
GSU-06
CIGADING 2
Kontruksi landsed indikasi retak lasnya request repair di gsu 06
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
137
14 Aug 2026
M. Zainudin
GSU-01
CIGADING 1
Spandek kontruksi indikasi sobek dan bolong request repair di dermaga D 1.4
RELEASE
REQUEST GANTI
Medium
Dokumentasi Dokumentasi
Completed
138
14 Aug 2026
M. Zainudin
Conveyor PBCN 1
CIGADING 1
Preventif mekanik sistem di PBCN 1 dan 2
Kondisi mekanik sistem masih oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
139
13 Aug 2026
M. Zainudin
Conveyor A102
CIGADING 2
Roll pembalik no 542 bag merak tabungnya bolong A102
RUSAK RINGAN
REQUEST GANTI
Medium
130000018648
Dokumentasi
In Process
140
13 Aug 2026
M. Zainudin
Conveyor A102
CIGADING 2
Roll pembalik no 488 bag merak tabungnya bolong A102
RUSAK RINGAN
REQUEST GANTI
Medium
130000018648
Dokumentasi
In Process
141
12 Aug 2026
Oka Aulia Yusuf
DLLC-02
CIGADING 1
Stopbar gantry hopper bagian laut pecah di DLLC 2. Request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018730
Dokumentasi
In Process
142
12 Aug 2026
Oka Aulia Yusuf
DLLC-02
CIGADING 1
Stopbar gantry hopper bagian darat pecah di DLLC 2. Request ganti
RELEASE
REQUEST GANTI
Medium
130000018729
Dokumentasi
Completed
143
08 Aug 2026
M. Zainudin
PHC-01
CIGADING 1
Kampas brake sistem closing bagian merak tipis di phc 2
RELEASE
REQUEST GANTI
Medium
130000018685
Dokumentasi
Completed
144
08 Aug 2026
M. Zainudin
DLLC-01
CIGADING 1
PHC 1 filter oli gate Hopper kotor request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018683
Dokumentasi
In Process
145
08 Aug 2026
M. Zainudin
PHC-01
CIGADING 1
Shafe roll boom indikasi tidak peresisi
RELEASE
REQUEST REPAIR
Medium
130000018684
Dokumentasi
Completed
146
08 Aug 2026
M. Zainudin
DLLC-01
CIGADING 1
Baud counter weight indikasi patah
RELEASE
REQUEST GANTI
Medium
130000018686
Dokumentasi
Completed
147
08 Aug 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Kampas brake sistem closing bagian merak tipis di phc 2. Req ganti
RELEASE
REQUEST GANTI
Medium
130000018685
Dokumentasi
Completed
148
07 Aug 2026
M. Zainudin
Conveyor PBCN 1
CIGADING 1
Preventif mekanik sistem di conveyor PBFC 1&2
Kondisi sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
149
06 Aug 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll pembalik no 608 bagian merak & anyer tabungnya patah di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018648
Dokumentasi
In Process
150
06 Aug 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll top no 681 bag merak macet di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018647
Dokumentasi
In Process
151
05 Aug 2026
M. Zainudin
CCSU
CIGADING 1
Preventive Mekanik system di area CCSU, sementara kondisi masih OK.
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
152
03 Aug 2026
Oka Aulia Yusuf
DLLC-03
CIGADING 1
Stopbar gantry bagian darat pecah di DLLC 3. Request ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018696
Dokumentasi
In Process
153
01 Aug 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
GSU 1 plat talang trucking retak & tipis (ganti)
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
154
01 Aug 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
GSU 4 kampas brake holding tipis sebelah (ganti)
RELEASE
REQUEST GANTI
Medium
Dokumentasi
Completed
155
30 Jul 2026
Oka Aulia Yusuf
Conveyor A101
CIGADING 2
A101 roll top no 1 tail sebelah darat macet (ganti)
RUSAK RINGAN
REQUEST GANTI
Medium
Dokumentasi
Outstanding
156
29 Jul 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Dinding di motor room bagian anyer ad yg bolong di dllc 1. Req repair
RELEASE
REQUEST REPAIR
Medium
Dokumentasi
Completed
157
29 Jul 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope maintrolley alur kiri rantas 3 kwt/str 6d=14kwt di gsu 5. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
Dokumentasi
Outstanding
158
28 Jul 2026
M. Zainudin
GSU-06
CIGADING 2
Wire rope grabe P7 rantas 4 kwt/str 6d=10kwt posisi grabe di gsu 06
RUSAK BERAT
REQUEST GANTI
Medium
Dokumentasi Dokumentasi
Outstanding
159
28 Jul 2026
M. Zainudin
GSU-06
CIGADING 2
Pulley landside bagian merak lasan retak di GSU6
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi Dokumentasi
Outstanding
160
25 Jul 2026
M. Zainudin
GSU-04
CIGADING 1
Buat tromol brake closing bagian kanan tidak ada 2pcs di GSU 4
RELEASE
REQUEST REPAIR
Medium
130000018606
Dokumentasi
Completed
161
25 Jul 2026
M. Zainudin
GSU-04
CIGADING 1
Wire rope grab C2 rantas 4kwt/str 6d=20kwt posisi grab di gsu 4
RELEASE
REQUEST GANTI
Medium
130000018605
Dokumentasi
Completed
162
25 Jul 2026
M. Zainudin
GSU-01
CIGADING 1
Preventif mekanik program shutdown inspection GSU 1
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
163
24 Jul 2026
M. Zainudin
Feeding SGT
CIGADING 1
Preventif mekanik system di feeding SGT
Kondisi bucket sebelah darat belum di ganti
Reducer kondisi Oke
Fieder kondisi Oke
RUSAK BERAT
REQUEST GANTI
Medium
130000018390
Dokumentasi
In Process
164
22 Jul 2026
M. Zainudin
Tower 2
CIGADING 1
Baud Tromol brake BCNO & C02 indikasi kendor dan patah di area tower 2. 130000018212[BCN0], 130000018581 [C02]
RELEASE
REQUEST GANTI
Medium
130000018212
Dokumentasi Dokumentasi
Completed
165
20 Jul 2026
M. Zainudin
CCSU
CIGADING 1
Preventif mekanik sistem di Ccsu
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
166
18 Jul 2026
M. Zainudin
DLLC-03
CIGADING 1
DLLC 3 Oli gearbox holding-closing keruh & berbusa (130000017862 [holding], 130000017866 [closing], 130000017863 [holding DLLC-04], 130000017867 [closing DLLC-04]
RELEASE
REQUEST GANTI
Medium
130000017862
Dokumentasi
Completed
167
16 Jul 2026
M. Zainudin
Conveyor A103
CIGADING 2
Karet legging drum head pulley(shuttle) bagian pinggir anyernya tipis di A103
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018594
Dokumentasi
In Process
168
16 Jul 2026
M. Zainudin
TFH & Feeding
CIGADING 1
Reducer di tfh oli nya rembes
RUSAK RINGAN
REQUEST PENAMBAHAN
Medium
130000018593
Dokumentasi
In Process
169
16 Jul 2026
M. Zainudin
Conveyor A103
CIGADING 2
Roll top no 65 bagian laut macet di tfh
RUSAK RINGAN
REQUEST GANTI
Medium
130000018592
Dokumentasi
In Process
170
16 Jul 2026
M. Zainudin
TFH & Feeding
CIGADING 2
Preventive mekanik program di conveyor A103 & tfh, running inspection pengecekan belt, drum, roll top & roll pembalik
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
171
15 Jul 2026
M. Zainudin
DLLC-02
CIGADING 1
DLLC 2 oli gearbox holding-closing berbusa keruh kondisi sudah tidak layak pakai. 130000017861 [holding], 130000017861 [closing]
KOTOR
REQUEST BERSIHKAN
Medium
130000017861
Dokumentasi Dokumentasi
In Process
172
15 Jul 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Preventive mekanik program di dllc 1, running inspection pengecekan wire rope holding & closing kondisi masih aman
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
173
15 Jul 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Preventive mekanik program di dllc 1, running inspection pengecekan kampas brake sistem holding, closing & luving kondisi masih aman
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
174
14 Jul 2026
M. Zainudin
Grabe Cigading 2
CIGADING 2
Grabe P4 lubang shaft lengan grabe bawah terkikis
RUSAK BERAT
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
175
14 Jul 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Grabe P4 lubang shaft lengan grabe bawah terkikis (repair)
RUSAK BERAT
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
176
14 Jul 2026
Oka Aulia Yusuf
Conveyor A101
CIGADING 2
Karet legging drum bend head shuttle ada yg terkelupas di A101. Req repair
RUSAK BERAT
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
177
13 Jul 2026
M. Zainudin
CCSU
CIGADING 1
Blade screw lepas 4 & banyak yang kendor
LAIK PAKAI
REQUEST FABRIKASI
-
130000018559
Dokumentasi
Completed
178
13 Jul 2026
M. Zainudin
CCSU
CIGADING 1
Cover shaft cc1 sebelah kanan terkikis mengakibatkan kan matrial bocor
LAIK PAKAI
REQUEST REPAIR
-
130000018547
Dokumentasi
Completed
179
13 Jul 2026
M. Zainudin
CCSU
CIGADING 1
CCSU, braket cc1 retak sebelah kanan
LAIK PAKAI
REQUEST REPAIR
-
130000018474
Dokumentasi
Completed
180
11 Jul 2026
M. Zainudin
PHC-02
CIGADING 1
Preventif mekanik program shutdown inspection mekanikal sistem PHC 1 & 2
- discharging sistem
- gantry umit
- holding-closing
- slewing
- luffing
- counter weight
Wire rope counter weight phc 1 (pantau) over all ok
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
181
11 Jul 2026
Oka Aulia Yusuf
PHC-01
CIGADING 1
Wire rope counter weight rantas 2kwt/str 6d=6kwt di phc 1. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
182
11 Jul 2026
Oka Aulia Yusuf
Grabe Cigading 1
CIGADING 1
Wire rope grab G1 rantas 3kwt/str 6d=5kwt posisi grab di phc 1. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
183
10 Jul 2026
M. Zainudin
Feeding SGT
CIGADING 1
Feeding, bucket elevator sebelah darat pecah 20pcs
RUSAK BERAT
REQUEST GANTI
Medium
130000018390
Dokumentasi Dokumentasi
In Process
184
09 Jul 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope auxtrolley rantas 2kwt/str 6d=5kwt di gsu 5. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
185
09 Jul 2026
M. Zainudin
Conveyor A102
CIGADING 2
A102 roll pembalik sebelah anyer no 508 bolong
RUSAK BERAT
REQUEST GANTI
Medium
130000018434
Dokumentasi
In Process
186
09 Jul 2026
M. Zainudin
GSU-06
CIGADING 2
Rell trolley gsu 06 indikasi Retak lasnya arah merak
RUSAK BERAT
REQUEST REPAIR
Medium
130000018524
Dokumentasi Dokumentasi
In Process
187
08 Jul 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Karet legging drum belt feeder bagian darat ad yg terkelupas di gsu 4. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018521
Dokumentasi
In Process
188
08 Jul 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Sambungan belt feeder ad yg terkelupas di gsu 4. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018522
Dokumentasi
In Process
189
07 Jul 2026
M. Zainudin
Conveyor A103
CIGADING 2
Preventif mekanik sistem di area 103 sementara kondisi masih Aman
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
190
07 Jul 2026
M. Zainudin
Conveyor A103
CIGADING 1
Pengukuran suhu Bearing drive sampai Tailpulley area conveyor 103
Sementara kondisi Ready to use
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
191
06 Jul 2026
M. Zainudin
DLLC-01
CIGADING 1
Preventif mekanik pengecekan mekanikal sistem DLLC1
Kondisi Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
192
06 Jul 2026
Oka Aulia Yusuf
DLLC-02
CIGADING 1
Kampas brake luffing terlalu rapet di DLLC 2. Request setting
LAIK PAKAI
REQUEST SERVICE
-
130000018523
Dokumentasi
Completed
193
02 Jul 2026
M. Zainudin
GSU-05
CIGADING 2
Wire rope holding rantas 6kwt/str 6d=10kwt di gsu 05. Req potong
RUSAK BERAT
REQUEST GANTI
Medium
130000018451
Dokumentasi Dokumentasi
In Process
194
02 Jul 2026
M. Zainudin
Conveyor A101
CIGADING 2
Preventif mekanik sistem di Grabe dan conveyor 101 sementara masih Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
195
02 Jul 2026
M. Zainudin
GSU-06
CIGADING 1
Wire rope holding rantas 4kwt/str 6d=15kwt di gsu 6.
RUSAK BERAT
REQUEST GANTI
Medium
130000018015
Dokumentasi
In Process
196
01 Jul 2026
Oka Aulia Yusuf
DLLC-04
CIGADING 1
Wire rope closing rantas 2kwt/str 6d=4kwt di dllc 4. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
197
30 Jun 2026
M. Zainudin
Conveyor A102
CIGADING 2
Belt conveyor A102 indikasi pinggirannya Sobek
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018525
Dokumentasi Dokumentasi
In Process
198
29 Jun 2026
M. Zainudin
PHC-01
CIGADING 1
Dinding motor room PHC 1 korosi bolong repair
RELEASE
REQUEST REPAIR
Medium
130000017589
Dokumentasi
Completed
199
27 Jun 2026
M. Zainudin
GSU-01
CIGADING 1
Grabe C3 fisik bengkok mekar (request ganti) posisi di gsu 1
RELEASE
REQUEST GANTI
Medium
130000018309
Dokumentasi
Completed
200
27 Jun 2026
M. Zainudin
Conveyor PBCN 1
CIGADING 1
PBCN 2 belt conveyor sobek (repair)
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018393
Dokumentasi
In Process
201
26 Jun 2026
M. Zainudin
Feeding SGT
CIGADING 1
Bucket elevator sebelah darat feeding SGT pecah 20 pcs & tipis 30 pcs (request ganti)
RELEASE
REQUEST GANTI
Medium
130000018390
Dokumentasi Dokumentasi
Completed
202
25 Jun 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventif mekanik sistem di Conveyor 102
Kondisi Roll Top dan pembalik kondisi Oke
Belt conveyor kondisi Oke
Dram leaging kondisi Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
203
25 Jun 2026
Oka Aulia Yusuf
CCSU
CIGADING 1
Program preventif mekanik NDT chain CC2
-Di tambah sebelum nya jadi total NDT 124 titik (100℅)
-Yang terindikasi lasan retak 50 titik (40.3℅)
RELEASE
REQUEST GANTI
Medium
Dokumentasi Dokumentasi
Completed
204
22 Jun 2026
M. Zainudin
DLLC-01
CIGADING 1
Anak Tangga grabe G4 indikasi Patah 2pcs
Posisi grabe di Dllc 01
RELEASE
REQUEST GANTI
Medium
130000018350
Dokumentasi
Completed
205
22 Jun 2026
Oka Aulia Yusuf
Grabe Cigading 1
CIGADING 1
Wire rope grab G2 rantas 4kwt/str 6d=15kwt. Request ganti (posisi grab di DLLC 2)
RELEASE
REQUEST GANTI
Medium
130000017945
Dokumentasi
Completed
206
20 Jun 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Wire rope grab p4 rantas 9kwt/str 6d=9kwt posisi grab ad di kade cgd 2. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018339
Dokumentasi
In Process
207
18 Jun 2026
Oka Aulia Yusuf
Conveyor A102
CIGADING 2
Roll pembalik no 544 bag merak tabungnya bolong di A102. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018201
Dokumentasi
In Process
208
13 Jun 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Cover bearing pulley auxtrolley bagian anyer lepas di auxtrolley unit gsu 4. Req repair
RELEASE
REQUEST REPAIR
Medium
130000018244
Dokumentasi
Completed
209
13 Jun 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Belt feeder bagian pinggir/anyer ada yg terkelupas di gsu 4. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018310
Dokumentasi
In Process
210
10 Jun 2026
M. Zainudin
PHC-01
CIGADING 1
Baud runningwheel counterweight sebelah kiri-Kanan patah 4pcs di PHC 1. Request ganti
RELEASE
REQUEST GANTI
Medium
130000018306
Dokumentasi Dokumentasi
Completed
211
10 Jun 2026
Oka Aulia Yusuf
Grabe Cigading 1
CIGADING 1
Wire rope grab G3 rantas 11kwt/str 6d=30kwt posisi grab di phc 2. Req ganti
RELEASE
REQUEST GANTI
Medium
130000018305
Dokumentasi
Completed
212
10 Jun 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Running wheel gate hopper bagian darat/anyer rusak 4 pcs di phc 2. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018331
Dokumentasi
In Process
213
10 Jun 2026
Oka Aulia Yusuf
PHC-02
CIGADING 1
Fiber pengarah wire rope closing bagian laut lepas/rusak di phc 2. Req ganti
RELEASE
REQUEST GANTI
Medium
130000018330
Dokumentasi
Completed
214
09 Jun 2026
Oka Aulia Yusuf
Conveyor A103
CIGADING 2
Roll top no 44 & 65 bagian anyer bearing nya rusak di A103. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018203
Dokumentasi
In Process
215
09 Jun 2026
M. Zainudin
Conveyor A103
CIGADING 2
Pengecekan di area 103
Kondisi Roll Oke
Kondisi Belt Oke
Kondisi suhu Bearing Oke
Dan kondisi Mekanik sistem Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
216
08 Jun 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Running wheel gate hopper bagian darat/laut rusak 12 pcs di dllc 1. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018326
Dokumentasi
In Process
217
06 Jun 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Safety pulley maintrolley di area pivot bagian anyer lasannya lepas di GSU-05. Request repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018251
Dokumentasi
In Process
218
06 Jun 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Roll preventing bagian anyer/laut bearingnya rusak di maintrolley unit gsu 5. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018247
Dokumentasi
In Process
219
05 Jun 2026
M. Zainudin
CCSU
CIGADING 1
Penambahan NDT 33 titik dan indikasi krack bertambah 14 titik
Total untuk sementara dari 124 titik yang terNDT 88 titik dan terindikasi krack 32 titik
RELEASE
REQUEST REPAIR
Medium
130000018269
Dokumentasi Dokumentasi
Completed
220
04 Jun 2026
Oka Aulia Yusuf
CCSU
CIGADING 1
Program NDT chain CC2
Dari total 124 titik chain, 55 titik di NDT terindikasi krack 18 titik. Request ganti
RELEASE
REQUEST GANTI
Medium
130000018269
Dokumentasi Dokumentasi
Completed
221
03 Jun 2026
M. Zainudin
DLLC-03
CIGADING 1
Grabe J1, wire rope grabe rantas 5kwt/strnd = 6d/13kwt posisi grabe di Dllc 3
RELEASE
REQUEST GANTI
Medium
130000018327
Dokumentasi
Completed
222
03 Jun 2026
Oka Aulia Yusuf
Grabe Cigading 1
CIGADING 1
Grab J4 anak tangga nya lepas 2pcs posisi grab di dllc 4. Req repair
LAIK PAKAI
REQUEST REPAIR
-
130000018216
Dokumentasi
Completed
223
03 Jun 2026
M. Zainudin
DLLC-03
CIGADING 1
Kondisi dinding motor room DLLC-03 keropos. Req. Repair
RELEASE
REQUEST REPAIR
Medium
130000017469
Dokumentasi Dokumentasi
Completed
224
02 Jun 2026
M. Zainudin
GSU-04
CIGADING 1
GSU 04 wire rope auxtrollely rantas 2kwt/strnd - 2kwt/6d
RUSAK RINGAN
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
225
02 Jun 2026
M. Zainudin
Conveyor A102
CIGADING 2
Roll Pembalik indikasi Bearing Rusak di Area 102 bagian anyer no 616 request ganti
RUSAK BERAT
REQUEST GANTI
Medium
130000018201
Dokumentasi
In Process
226
02 Jun 2026
M. Zainudin
Conveyor A102
CIGADING 2
Roll Top indikasi Bearing Rusak di Area 102 bagian anyer request ganti
RUSAK BERAT
REQUEST GANTI
Medium
130000018200
Dokumentasi
In Process
227
02 Jun 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Cover bearing pulley auxtrolley bagian anyer lepas di auxtrolley unit gsu 4. Req repair
RELEASE
REQUEST REPAIR
Medium
Dokumentasi
Completed
228
30 May 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
Kondisi kontruksi dinding gilder bagian darat/merak ada yg bolong di gsu 1. Req repair
RELEASE
REQUEST REPAIR
Medium
Dokumentasi
Completed
229
30 May 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
Handrail bagian land side darat/merak ada yg rusak di gsu 1. Req repair
RELEASE
REQUEST REPAIR
Medium
Dokumentasi
Completed
230
30 May 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
gearbox holding oli nya di bwh level min di gsu 1. Req tambah oli
RELEASE
REQUEST PENAMBAHAN
Medium
Dokumentasi
Completed
231
29 May 2026
M. Zainudin
Conveyor C02
CIGADING 1
Kondisi oli reducer drive conveyor C02 kondisi Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
232
29 May 2026
M. Zainudin
Tower 2
CIGADING 1
Oli reducer drive conveyor BCNO arah Darat-Laut indikasi Kotor &Berbusa request Ganti
RELEASE
REQUEST GANTI
Medium
130000018182
Dokumentasi Dokumentasi
Completed
233
29 May 2026
M. Zainudin
Conveyor PBCN 1
CIGADING 1
Clening magnet elevator di Pbcn 01&02 sementara kondisi Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
234
29 May 2026
M. Zainudin
Conveyor PBCN 1
CIGADING 1
Belt conveyor Pbcn 02 indikasi Terkelupas request repair
RUSAK BERAT
REQUEST REPAIR
Medium
130000018184
Dokumentasi Dokumentasi
In Process
235
26 May 2026
Oka Aulia Yusuf
Conveyor A103
CIGADING 2
Roll pembalik no 48 bag anyer tabungnya bolong di A103. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018003
Dokumentasi
In Process
236
26 May 2026
Oka Aulia Yusuf
Conveyor A103
CIGADING 2
Roll pembalik no 51 bag merak gompal/rusak di A103. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
130000018003
Dokumentasi
In Process
237
25 May 2026
M. Zainudin
DLLC-04
CIGADING 1
Preventif mekanik sistem di DLLC-04
wire rope holding-closing kondisi Oke
Breake holding-closing kondisi Oke
Lubrikasi kondisi Oke , Ready to use
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
238
23 May 2026
M. Zainudin
CCSU
CIGADING 1
"Hasil pengecekan preventif mekanik di area CC2 ditemukan 4 sovel patah, 3 sebelah kiri & 1 sebelah kanan. Request ganti"
RELEASE
REQUEST GANTI
Medium
Dokumentasi Dokumentasi
Completed
239
22 May 2026
M. Zainudin
Conveyor C02
CIGADING 1
Baut tromol brake conv. C02 bagian merak patah 2pcs. Request ganti
RELEASE
REQUEST GANTI
Medium
130000017987
Dokumentasi Dokumentasi
Completed
240
22 May 2026
M. Zainudin
Conveyor BCNO
CIGADING 1
Baut tromol brake conv. BCNO bagian merak kendor 10pcs dan patah 2pcs (Request ganti).
RELEASE
BY EXECUTOR
Medium
130000017715
Dokumentasi Dokumentasi
Completed
241
21 May 2026
M. Zainudin
GSU-06
CIGADING 2
Preventif mekanik sistem di GSU-06
Wire rope kondisi Oke
Brake holding-closing kondisi Oke
Pulley holding-closing kondisi Oke
Tell trolley kondisi Oke
Wearing plate kondisi oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
242
21 May 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Kampas brake sistem closing bagian merak darat tipis di gsu 5. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
Dokumentasi
Outstanding
243
21 May 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Baut dudukan drum holding bagian anyer patah 1 pcs di gsu 5. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
Dokumentasi
Outstanding
244
21 May 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Baut dudukan drum holding bagian anyer patah 1 pcs di gsu 5. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
Dokumentasi
Outstanding
245
20 May 2026
M. Zainudin
CCSU
CIGADING 1
Preventif mekanik sistem di CCSU
Kondisi mekanik sistem Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
246
19 May 2026
M. Zainudin
Conveyor A101
CIGADING 2
Preventif di conveyor A101
Kondisi oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
247
18 May 2026
M. Zainudin
Grabe Cigading 1
CIGADING 1
Preventif mekanik sistem di PHC 01 terdapat anak tangga grabe G1 patah
RELEASE
REQUEST REPAIR
Medium
130000014757
Dokumentasi
Completed
248
18 May 2026
M. Zainudin
PHC-01
CIGADING 1
Preventif mekanik sistem di PHC 01
Wire rope grabe no G1
Indikasi rantas
RELEASE
REQUEST GANTI
Medium
130000018127
Dokumentasi Dokumentasi
Completed
249
13 May 2026
M. Zainudin
DLLC-04
CIGADING 1
Preventif mekanik sistem di DLLC 04
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
250
12 May 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventif mekanik sistem di area 102
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
251
11 May 2026
M. Zainudin
DLLC-02
CIGADING 1
Preventif mekanik sistem di DLLC 2
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
252
09 May 2026
M. Zainudin
Conveyor A103
CIGADING 2
Preventif mekanik sistem di area Conveyor A103
Sementara masih kondisi Oke
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi Dokumentasi
Ready to Use
253
07 May 2026
Oka Aulia Yusuf
CCSU
CIGADING 1
Dudukan Rell Chain CC2 yang rusak di Crane CSU.
RELEASE
REQUEST REPAIR
Medium
130000018054
Dokumentasi Dokumentasi
Completed
254
07 May 2026
Oka Aulia Yusuf
CCSU
CIGADING 1
Team Preventive Supporting Mekanik Executor dengan melakukan pengecekan dan pembukaan cover nomor 2 dan nomor 3 untuk memastikan kondisi chain, rel, dan shovel di area CC2. Kerusakan yang ditemukan sudah langsung di eksekusi Eksekutor Mekanik
RELEASE
REQUEST REPAIR
TIDAK
130000018054
Dokumentasi
Completed
255
05 May 2026
M. Zainudin
GSU-04
CIGADING 1
Supporting Team Vulkanisir Executor Repair Belt Feeder di GSU-04
RUSAK BERAT
PREVENTIVE MAINTENANCE
Medium
130000018012
Dokumentasi Dokumentasi
In Process
256
05 May 2026
Ayu Andini
CCSU
CIGADING 1
Pengecekan Preventive dan Supporting Team Mekanik Executor di CC2 CSU
RELEASE
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Completed
257
05 May 2026
M. Zainudin
GSU-06
CIGADING 2
Rell Troley GSU-06 terindikasi retak lasannya di sebelah merak-anyer.
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017779
Dokumentasi
In Process
258
05 May 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Sackle safety meja vibrating bagian anyer tipis di gsu 5. Req ganti
RUSAK RINGAN
REQUEST GANTI
Medium
130000018039
Dokumentasi
In Process
259
04 May 2026
M. Zainudin
GSU-01
CIGADING 1
Brake system closing bagian anyer indikasi pegasnya retak di gsu 01
RELEASE
REQUEST GANTI
Medium
130000017880
Dokumentasi Dokumentasi
Completed
260
04 May 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Sambungan belt feeder ada yg terkelupas di gsu 4. Req repair
RUSAK BERAT
REQUEST REPAIR
Medium
130000018012
Dokumentasi
In Process
261
04 May 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Karet skatebord gate bagian belakang lepas di gsu 4. Req repair
RUSAK BERAT
REQUEST REPAIR
Medium
130000018013
Dokumentasi
In Process
262
04 May 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventif mekanik sistem di conveyor 102
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
263
01 May 2026
M. Zainudin
Conveyor A102
CIGADING 2
Preventive bearing drum dan motor reducer di area conveyor A102
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
264
30 Apr 2026
M. Zainudin
CCSU
CIGADING 1
Suhu bearing drum sementara kondisi masih aman
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
265
30 Apr 2026
M. Zainudin
Conveyor C02
CIGADING 1
Baud tromol brake indikasi patah
RELEASE
REQUEST GANTI
Medium
130000017987
Dokumentasi
Completed
266
28 Apr 2026
M. Zainudin
Conveyor PBCN 2
CIGADING 1
Belt conveyor terkelupas di PBCN-02. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017973
Dokumentasi
In Process
267
25 Apr 2026
M. Zainudin
PHC-02
CIGADING 1
Oli gearbox holding closing luffing PHC-02 masih dalam kondisi baik
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
268
25 Apr 2026
M. Zainudin
PHC-01
CIGADING 1
Oli gearbox holding closing luffing PHC 1 masih dalam kondisi baik
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi Dokumentasi
Ready to Use
269
25 Apr 2026
M. Zainudin
PHC-02
CIGADING 1
Pengecekan gearbox holding closing luffing PHC 2
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
270
25 Apr 2026
M. Zainudin
PHC-01
CIGADING 1
Pengecekan gearbox holding-closing PHC 1
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
271
23 Apr 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Wire rope grab P7 rantas 2kwt/str 6d=12kwt. Request ganti
RUSAK BERAT
REQUEST GANTI
Medium
130000017243
Dokumentasi
In Process
272
23 Apr 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Wire rope grab C3 rantas 4kwt/str 6d=10kwt di cgd 2. Req ganti
RUSAK BERAT
REQUEST GANTI
Medium
130000017957
Dokumentasi
In Process
273
23 Apr 2026
Oka Aulia Yusuf
Grabe Cigading 2
CIGADING 2
Dinding bucket bagian laut grab C3 ada yg bolong di cgd 2. Req repair
RUSAK BERAT
REQUEST REPAIR
Medium
130000017959
Dokumentasi
In Process
274
23 Apr 2026
M. Zainudin
Grabe Cigading 2
CIGADING 2
Safety pulley pillowblock bagian atas anyer darat las-lasan lepas di grab P3 Cigading 2. Request repair
RUSAK BERAT
REQUEST REPAIR
Medium
130000017958
Dokumentasi Dokumentasi
In Process
275
22 Apr 2026
M. Zainudin
Grabe Cigading 1
CIGADING 1
Grabe J1 posisi di DLLC 4, wire rope Grabe rantas 3kwt/strnd = 6d/13kwt request ganti.
(temuan sebelumnya : 02.04.2026)
RELEASE
REQUEST GANTI
Medium
130000017775
Dokumentasi Dokumentasi
Completed
276
21 Apr 2026
M. Zainudin
GSU-06
CIGADING 2
Shutdown inspection gsu 6
Rail trolley lasan retak
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017779
Dokumentasi
In Process
277
21 Apr 2026
M. Zainudin
GSU-06
CIGADING 2
Shutdown inspection gsu 6
Wearing plat lepas baut patah
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017950
Dokumentasi
In Process
278
21 Apr 2026
M. Zainudin
GSU-06
CIGADING 2
Shutdown inspection GSU 6
Stop bar gantry bagian darat-metak tidak ada/terlepas
RUSAK RINGAN
REQUEST GANTI
Medium
130000017949
Dokumentasi
In Process
279
21 Apr 2026
Oka Aulia Yusuf
GSU-05
CIGADING 2
Wire rope holding rantas 2kwt/str 6d=10kwt di gsu 5. Req ganti Di drum gk ada spare nya
RUSAK BERAT
REQUEST GANTI
Medium
130000017947
Dokumentasi
In Process
280
20 Apr 2026
Oka Aulia Yusuf
DLLC-01
CIGADING 1
Grease autolub berkurang di DLLC-01. Request penambahan
RELEASE
REQUEST PENAMBAHAN
PANTAU
130000017666
Dokumentasi
Completed
281
20 Apr 2026
M. Zainudin
DLLC-01
CIGADING 1
Wire rope grab G2 rantas 3 kwt/str 6d=11kwt posisi grab ad di dllc 1. Req ganti
RELEASE
REQUEST GANTI
Medium
130000017945
Dokumentasi
Completed
282
18 Apr 2026
Oka Aulia Yusuf
GSU-04
CIGADING 1
Struktur Gantry GSU-04 korosi, req. Perbaikan
RUSAK RINGAN
REQUEST REPAIR
Medium
130000018049
Dokumentasi Dokumentasi
In Process
283
18 Apr 2026
M. Zainudin
GSU-04
CIGADING 1
GSU 4 gorden corong arah trucking lepas. Request Repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017988
Dokumentasi Dokumentasi
In Process
284
18 Apr 2026
M. Zainudin
GSU-04
CIGADING 1
GSU-04 guide rell maintrolley bagian darat-merak indikasi bearing rusak/oblak. Req. Ganti
RELEASE
REQUEST GANTI
Medium
130000017922
Dokumentasi
Completed
285
18 Apr 2026
Oka Aulia Yusuf
GSU-01
CIGADING 1
Girder boom bagian darat merak bolong indikasi korosi di GSU 1. Request repair
RELEASE
REQUEST REPAIR
Medium
130000017921
Dokumentasi Dokumentasi
Completed
286
17 Apr 2026
M. Zainudin
CONV BCNO
CIGADING 1
BCNO counter weight bolong korosi belum di perbaiki
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
287
17 Apr 2026
M. Zainudin
CONV C02
CIGADING 1
C02 tromol brake baut yang patah belum di ganti. Request Ganti
RELEASE
REQUEST GANTI
Medium
Dokumentasi
Completed
288
15 Apr 2026
M. Zainudin
PHC-01
CIGADING 1
PHC 1 baut counter weight patah 2 pcs bagian bawah-darat request ganti. Langsung di eksekusi oleh tim Mekanik
RELEASE
REQUEST GANTI
Medium
130000017918
Dokumentasi Dokumentasi
Completed
289
14 Apr 2026
M. Zainudin
Conveyor A102
CIGADING 2
Leggingan drum bend head bagian merak di A102 sobek. Request repair
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
290
14 Apr 2026
M. Zainudin
Grabe Cigading 2
CIGADING 2
Wire rope Grabe G2 rantas 2kwt/str 6d=7kwt posisi grab di dllc 1. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
291
13 Apr 2026
M. Zainudin
GSU-01
CIGADING 1
Brake system closing bagian anyer indikasi pegasnya retak di GSU-01. Req ganti
RELEASE
REQUEST GANTI
Medium
130000017880
Dokumentasi
Completed
292
13 Apr 2026
M. Zainudin
GSU-01
CIGADING 1
Belt feeder Gsu-01 indikasi sobek request Repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017833
Dokumentasi
In Process
293
31 Mar 2026
M. Zainudin
Conveyor A101
CIGADING 2
Inspeksi Ringdisk A101 Maret 2026

Head darat: ok
Head laut: ok
Bend head darat: ok
Bend head laut : ok
Snub head darat : ok
Snub head laut: ok
Drive darat : ok
Drive laut: ok
Snub drive darat: ok
Snub drive laut: ok
Bend 1 darat: ok
Bend 1 laut: ok
Bend 2 darat : ok
Bend 2 laut: ok
Bend 3 darat: ok
Bend 3 laut: ok
Take up 1 darat: ok
Take up 1 laut: ok
Take up 2 darat: ok
Take up 2 laut: ok
Tail darat: ok
Tail laut : ok
Catatan hasil pengecekan ringdisk A101 kondisi masih OK
LAIK PAKAI
PREVENTIVE MAINTENANCE
TIDAK
Dokumentasi
Ready to Use
294
31 Mar 2026
M. Zainudin
GSU-06
CIGADING 2
Wire rope closing rantas 2kwt/str 6d=3kwt di gsu 6. Pantau
LAIK PAKAI
PREVENTIVE MAINTENANCE
PANTAU
Dokumentasi
Ready to Use
295
31 Mar 2026
M. Zainudin
GSU-06
CIGADING 2
Rail trolley retak bagian kiri & kanan di gsu 6. Req repair
RUSAK RINGAN
REQUEST REPAIR
Medium
Dokumentasi
Outstanding
296
17 Mar 2026
M. Zainudin
CONV C02
CIGADING 1
Preventif mekanik sistem di area C02. indikasi baud tromol brake patah
RUSAK RINGAN
REQUEST GANTI
Medium
Dokumentasi Dokumentasi
Outstanding
297
17 Mar 2026
M. Zainudin
CONV BCNO
CIGADING 1
Preventif mekanik sistem di area BCNO, indikasi baud tromol brake patah.
RUSAK RINGAN
REQUEST GANTI
Medium
130000017715
Dokumentasi Dokumentasi
In Process
298
13 Mar 2026
M. Zainudin
CCSU
CIGADING 1
CCSU tangga HLSKT patah request di perbaikan. Sudah di eksekusi oleh Mekanik Shift
LAIK PAKAI
PREVENTIVE MAINTENANCE
-
Dokumentasi
Outstanding
299
13 Mar 2026
M. Zainudin
CCSU
CIGADING 1
Mengamankan patahan sovel CC2
CC2 sovel patah 1 pcs request ganti
RELEASE
REQUEST GANTI
Medium
Dokumentasi
Completed
300
13 Mar 2026
M. Zainudin
CCSU
CIGADING 1
Terdapat lubang pada dinding transfer material dari CC3 ke CC3 posisi di slip ring request perbaikan
RELEASE
REQUEST REPAIR
Medium
Dokumentasi Dokumentasi
Completed
301
12 Mar 2026
M. Zainudin
Conveyor A102
CIGADING 2
A102 roll pembalik bagian anyer no 502 macet "ganti"
RUSAK BERAT
REQUEST GANTI
Medium
130000017536
Dokumentasi Dokumentasi
In Process
302
12 Mar 2026
M. Zainudin
Conveyor A102
CIGADING 2
A102 roll pembalik bagian anyer no 693 tabung patah "ganti"
RUSAK BERAT
REQUEST GANTI
Medium
130000017536
Dokumentasi
In Process
303
03 Mar 2026
M. Zainudin
GSU-06
CIGADING 2
Rell trolley gsu 06 indikasi Retak lasnya arah anyer. Request repair
RUSAK RINGAN
REQUEST REPAIR
Medium
130000017587
Dokumentasi
In Process
304
03 Mar 2026
M. Zainudin
GSU-06
CIGADING 2
Wire rope holding rantas 3 kwt/str 6d=10kwt di gsu 6. Request ganti(Potong)
RUSAK BERAT
REQUEST GANTI
Medium
130000017588
Dokumentasi
In Process
305
02 Mar 2026
M. Zainudin
PHC-01
CIGADING 1
Pintu bagian belakang ruang motor room macet gak bisa ditutup akibat korosi. req perbaikan agar air hujan tidak masuk ke ruang motor room
RUSAK BERAT
REQUEST REPAIR
Medium
130000017580
Dokumentasi
In Process
306
02 Mar 2026
M. Zainudin
PHC-01
CIGADING 1
Kondisi ruang trafo PHC-01 terdapat bekas genangan air , ada kemungkinan bocor dari titik yang sama. Rekues repair
RELEASE
REQUEST REPAIR
Medium
130000017361
Dokumentasi
Completed